Rotech Subsea completes significant cable de-burial and post-lay trenching works at North Sea wind farm

View all news from: Rotech Subsea Ltd
View directory entry for: Rotech Subsea Ltd

04 May 2021

Subsea trenching and excavation pioneer, Rotech Subsea, has successfully completed a major cable de-burial and post-lay trenching scope for an offshore energy market solutions leader at a key offshore wind farm in the British North Sea. Aberdeen-based Rotech Subsea’s state-of-the-art RS2 jet trenching tool was deployed to complete the works from its north east HQ in Q4, 2020.

Rotech Subsea were contracted to carry out cable de-burial and post-lay trenching works on multiple sections of the offshore wind farm. The client requested Rotech’s RS2 for the de-burial of cables in one section which were buried 1.5m below Mean Sea Bed Level. The jet trenching tool was also deployed for the burial work of cables in another sector of the OWF which were required to be buried to client specification of 1.5m top of cable.

The subsea spread of equipment was mobilised in Q4, 2020 with the Controlled Flow Excavation tool operating in water depths of up to 32m LAT. Soil conditions in the de-burial sector were loose with the presence of clay.

The project was a great success with the client delighted with the RS2’s technical and performance capabilities which contributed to a saving on total project costs. The RS2 excelled in de-burial and burial operations, finding no issues in the harder areas where there could have been the presence of clay.

The RS2 reached client de-burial specification with ease, achieving it in one pass at a progress rate of 4.8m/min. In the post-lay trenching areas some sections were softer than expected resulting in rapid backfill of about 0.7m. This was no issue at a progress rate of 3m/min with the RSE Controlled Flow excavator achieving between 2.2m-2.5m BOT allowing for the cable to fall to its 1.5m TOC burial specification in just one pass.